PPAP (Production Part Approval Process) originated in the automotive industry and is now also used in construction machinery, agricultural machinery, trailers and appliances. Its purpose is to prove that the supplier understands customer requirements and can meet them consistently in series production. Unlike first article inspection (FAI), it approves the production process, not just the first part.

When Is PPAP Required?

  • New part or new supplier
  • Drawing or specification change
  • Change of material, sub-supplier or production site
  • New tooling, fixture or equipment
  • Restart of a part not produced for a long time (typically 12 months)

The 18 PPAP Elements

NoElementFor a welded part
1Design recordsApproved drawing with weld symbols
2Engineering change documentsRevision approvals
3Customer engineering approvalIf required
4Design FMEAIf the supplier is design-responsible
5Process flow diagramCutting, bending, fit-up, welding, inspection, surface treatment
6Process FMEAWeld defects, distortion, wrong assembly risks
7Control planInspection method, frequency and reaction plan per step
8Measurement system analysis (MSA)Gage R&R for gauges and check fixtures
9Dimensional resultsBallooned drawing and full dimensional report
10Material and performance test resultsMaterial certificates, weld macro sections, tensile or fatigue tests
11Initial process studiesCpk/Ppk for critical dimensions
12Qualified laboratory documentationAccredited lab certificates
13Appearance approval reportFor painted or visible surfaces
14Sample partsParts made under series conditions
15Master sampleRetained approved part
16Checking aidsCheck fixtures and gauges
17Customer-specific requirementsAdditional requirements from the customer manual
18Part submission warrant (PSW)Summary document signed by the supplier

Five Submission Levels

LevelSubmitted to customer
1PSW only
2PSW with samples and limited supporting data
3PSW with samples and complete supporting data (default)
4PSW and other requirements defined by the customer
5PSW, samples and complete data reviewed at the supplier’s site

What Is Specific to Welded Parts

  • WPS and welder qualification: the WPSs and welder certificates used in series production go into the PPAP file. A parameter change can trigger a new PPAP.
  • Macro cut-and-etch test: sections through critical welds show penetration, throat and fusion. In automotive, this test is repeated at set intervals throughout production.
  • Fixtures: series repeatability rests on the welding fixture. Fixture verification and maintenance belong in the control plan.
  • Distortion: post-weld change of critical dimensions shows up in the Cpk study. Capability cannot be reached until the welding sequence is fixed.
  • Surface treatment: if painting or galvanizing is done by a sub-supplier, that supplier's process approval is part of the chain.

Welding Risks in the PFMEA

A good PFMEA covers typical welding failure modes: missing weld, weld in the wrong position, undersized throat, lack of fusion, cracks, porosity, excessive spatter, distortion and wrong material. Each needs a prevention control (fixture, poka-yoke, WPS) and a detection control (VT, gauge, macro test).

PPAP vs FAI

FAI verifies that a single part conforms to the drawing. PPAP proves that the process can produce conforming parts consistently at a given rate. Outside automotive, buyers often start with FAI and ask for a PPAP-like approval as volumes grow.

At ArmaWeld: for series welded parts we prepare the initial approval file with process flow, control plan, ballooned dimensional report and macro section tests. Steps we coordinate with partners, such as cutting, bending or painting, are shown in the process flow. Level and contents follow the customer's manual. Read our first article approval guide →

Frequently Asked Questions

Is PPAP only used in automotive?

No. It started there, but construction and agricultural machinery, trailer, appliance and electrical equipment makers also ask for PPAP or similar processes.

What is a PSW?

The Part Submission Warrant is the summary document in which the supplier declares and signs that the part meets all requirements. Customer approval is given on the PSW.

Does a welding parameter change require a new PPAP?

The customer must be notified. Depending on the impact, the customer may request a new submission. WPS changes should therefore be controlled.

How many samples are produced for PPAP?

Under series conditions, typically at least one hour or 300 pieces of production. For large welded parts the quantity is agreed with the customer.