The force a hydraulic cylinder produces is transferred to the machine through two small connection points: the brackets on the barrel side and on the rod end. They are small compared with the rest of the welded part, yet they are among the most heavily stressed and most frequently cycled areas of the machine. Many cracks and much pin and bushing wear in the field start here.

Typical Bracket Types

  • Clevis: two parallel plates with a pin through them.
  • Single lug: a single plate that fits into the cylinder's clevis, often with a spherical bearing.
  • Trunnion block: a two-bearing mount carrying the cylinder from its middle.
  • Foot mount: a base plate to which the cylinder is bolted.

Pin Bore Alignment

In a clevis, the holes in the two plates must be coaxial so the pin goes in without binding and the bushings wear evenly. During welding the plates pull inwards and the holes shift. Precision pin bores are therefore usually machined after welding in a single setup; if holes are made before welding, machining allowance is left (see post-weld machining). Alignment between the brackets at both cylinder ends also matters, so that no side load reaches the cylinder rod.

Welding and Fatigue

Cylinder brackets are loaded and unloaded every working cycle: a fatigue load. The weld detail is the main driver of fatigue life:

  • Attaching lug plates to the main body with full penetration gives a higher fatigue class than fillet welds (see fatigue and FAT class).
  • Weld stops away from plate corners (wrap-around, no stopping at the corner).
  • Toe grinding or TIG dressing where needed (see weld grinding).
  • Back-up reinforcement that spreads load; no lugs welded directly to thin sheet.

Bushings and Lubrication

A replaceable bushing is normally pressed into the pin bore. The bore tolerance (press fit), grease groove and grease nipple hole must be defined on the drawing. Bushings are pressed after painting; paint must not enter the bore.

Inspection

  • VT and MT on lug welds; UT on full-penetration welds.
  • Pin hole centre distance, coaxiality and diameter.
  • Installed distance between the two cylinder mounts.

At ArmaWeld: we weld bodies with cylinder brackets to drawing and our ISO 9712 Level 2 staff carry out MT and UT. Post-weld machining of pin bores is coordinated with our partner machine shops and bore dimensions are reported. Machine frame manufacturing →

Frequently Asked Questions

Should pin holes be made before or after welding?

Precision bores are usually machined after welding in one setup; if made before, machining allowance is left.

Why do cylinder brackets crack?

Load changes every cycle, causing fatigue; poor weld details and weld stops at corners are the main causes.

When are bushings pressed in?

After painting; paint must not enter the bore.

Which NDT is used on brackets?

VT and MT; UT on full-penetration welds.

Do you have welded parts with cylinder mounts?

Send the drawing; we will quote welding, machining and inspection.

Request a Quote →