A WPQR (Welding Procedure Qualification Record) is a document certified by test results that proves a welding procedure delivers the required mechanical properties. A WPS (Welding Procedure Specification) only defines how to weld; the WPQR proves that the procedure actually achieves the desired properties.

Fundamental rule: Companies manufacturing under EN ISO 3834-2 and EN 1090-2 must link every WPS to a valid WPQR. Welding with an unqualified procedure is not acceptable.

Difference Between WPS and WPQR

DocumentContentPurpose
WPSCurrent, voltage, gas, electrode, pass sequence, preheatInstructions to the welder on the shop floor
WPQRTest coupon results: tensile, bend, hardness, Charpy, macroProve validity of the procedure
CertificateSignature of independent inspection body (TÜV, BV, DNV)Third-party approval

EN ISO 15614-1: Qualification Process for Steel

Welding procedure qualification for steel is performed under EN ISO 15614-1. The process involves:

  1. Prepare pWPS (preliminary WPS): Draft welding parameters.
  2. Weld the test piece: Using production equipment and personnel under workshop conditions.
  3. Non-destructive examination (NDE): Visual (VT), penetrant (PT), ultrasonic (UT) or radiographic (RT).
  4. Destructive tests: Tensile, bend, hardness survey, Charpy impact, macro examination.
  5. Write and approve WPQR: All results recorded; if acceptable, WPS is formally qualified.

Required Tests

TestAcceptance CriterionStandard
TensileRm ≥ minimum UTS of base metalEN ISO 4136
Bend4 specimens, 180°, no cracksEN ISO 5173
Charpy V-NotchAverage energy at WPS temperature ≥ 27 JEN ISO 9016
HardnessHV10 — max 380 HV for structural steel (450 HV for S960QL)EN ISO 9015-1
Macro examinationNo cracks, porosity or lack of penetrationEN ISO 17639

Range of Approval

A WPS qualified by a WPQR covers a limited range of application. Any weld outside that range needs a new qualification:

  • Material group: by ISO/TR 15608 group number (1.1, 1.2, 2, 3, 8.1 etc.). A test in one group also covers certain other groups according to the table in the standard.
  • Thickness: for a test piece of 3–12 mm, roughly 0.5t (minimum 3 mm) to 2t; for 12–100 mm, 0.5t to 2t. For single-run or high heat input welds the upper limit is narrower.
  • Diameter (pipe): a range starting at half the test diameter is qualified; for small diameters both the lower and upper limits are narrower.
  • Position: without impact or hardness requirements, a test in one position covers all others except vertical down (PG); with such requirements the positions with the highest and lowest heat input must be tested.
  • Consumables, gas and heat input: where impact requirements apply, heat input may be at most 25% higher than in the test; where hardness requirements apply, at most 25% lower.

Important: EN ISO 15614-1 covers steels and nickel alloys. Welding procedures for aluminium and its alloys are qualified to EN ISO 15614-2. Always check the current tables of the standard for exact ranges.

Routes to Qualify a WPS: EN ISO 15607

Not every welding procedure needs a laboratory test. EN ISO 15607 defines five ways to qualify a WPS:

StandardRouteWhen is it used?
EN ISO 15614Welding procedure testThe most comprehensive route. Usually mandatory for EXC3, EXC4 and pressure equipment.
EN ISO 15613Pre-production welding testWhen a standard test piece cannot represent the real part, a part-like sample is welded.
EN ISO 15612Standard welding procedureUse of a published standard procedure; for low-risk work and limited materials.
EN ISO 15611Previous welding experienceThe manufacturer documents successful past production with the same procedure.
EN ISO 15610Tested welding consumablesBased on consumable approval; the most limited route.

Under EN 1090-2, routes 15610, 15611 and 15612 can be accepted in EXC2 for certain materials and conditions. In EXC3 and EXC4, procedures must be qualified by an EN ISO 15614-1 test or an EN ISO 15613 pre-production test. So on a project with a high execution class it is not enough for a supplier to say "we have WPQRs"; ask which route they were qualified by.

EN ISO 15614-1:2017 Level 1 and Level 2

The 2017 edition of the standard introduced two test levels:

  • Level 1: closer to the ASME IX approach; fewer tests and a wider range of approval.
  • Level 2: the traditional European approach; with impact and hardness tests it gives a narrower but more reliable range of approval.

A procedure qualified to level 2 also covers level 1, but not the other way round. Work under EN 1090-2 is based on level 2. When you review a WPQR, the level it was issued to is one of the first things to check.

Validity of a WPQR

A WPQR qualified under EN ISO 15614 is indefinitely valid — no renewal required. However, re-qualification is needed if:

  • The welding process changes (e.g. MAG to TIG)
  • The material group changes
  • Thickness exceeds the qualified range
  • Consumables change significantly

ArmaWeld WPS/WPQR Library

ArmaWeld holds 80+ approved WPS and WPQR records covering carbon steel (S235–S355), high-strength (S690QL, S700MC, S960QL), stainless (304L, 316L), aluminium alloys (5083, 6082) and wear steels (HARDOX 400/450/500).

Checklist for Reviewing a Supplier's WPQRs

When your purchasing or quality team reviews a supplier's WPQR list, ask these questions:

  1. Process: is the process for your part (for example 135 or 121) on the list?
  2. Material group: is your steel (for example S355 group 1.2, S690QL group 3) within the qualified groups?
  3. Thickness and diameter: are your thinnest and thickest parts within the qualified range?
  4. Joint type: a butt weld qualification covers fillet welds, but not the other way round. If you have full-penetration butt welds, a butt weld qualification is required.
  5. Impact test temperature: if the project requires impact values at -20 °C or -40 °C, the WPQR must have been tested at that temperature.
  6. Heat treatment: if the project requires PWHT, the WPQR must have been made on a heat-treated test piece.
  7. Examining body and level: who signed the document, and to which standard and level was it issued?

How Long Does a WPQR Take?

Welding the test piece and non-destructive testing are usually finished within a few days. Destructive tests can take one to three weeks depending on the laboratory's workload. For a material or thickness without a qualification, this time has to be planned at quotation stage. With a supplier whose existing WPQRs already cover your job, the waiting time disappears completely.

At ArmaWeld: at quotation stage we compare your drawing with our existing WPS/WPQR list. If no procedure covers your job, we state this clearly in the quotation and add the test time to the delivery schedule. See our quality and certificates →

Frequently Asked Questions

What is the difference between a WPS and a WPQR?

A WPS is the instruction that tells the welder how to weld. A WPQR is the record of the inspection and test results of a test piece welded to that instruction, proving that the procedure works.

Does a WPQR expire?

A WPQR qualified to EN ISO 15614-1 does not expire. But if an essential variable (process, material group, thickness range, heat treatment and so on) changes, a new qualification is needed.

Who approves a WPQR?

An independent examining body (for example TÜV, Bureau Veritas, DNV) that witnesses the tests and evaluates the results. For pressure equipment this body must be a notified body or a recognised third-party organisation.

Can a WPQR be used by another company?

No. A WPQR is tied to the manufacturer that carried out the test and to its technical control. Another company's WPQR cannot be taken over.