A WPQR (Welding Procedure Qualification Record) is a document certified by test results that proves a welding procedure delivers the required mechanical properties. A WPS (Welding Procedure Specification) only defines how to weld; the WPQR proves that the procedure actually achieves the desired properties.
Fundamental rule: Companies manufacturing under EN ISO 3834-2 and EN 1090-2 must link every WPS to a valid WPQR. Welding with an unqualified procedure is not acceptable.
Difference Between WPS and WPQR
| Document | Content | Purpose |
|---|---|---|
| WPS | Current, voltage, gas, electrode, pass sequence, preheat | Instructions to the welder on the shop floor |
| WPQR | Test coupon results: tensile, bend, hardness, Charpy, macro | Prove validity of the procedure |
| Certificate | Signature of independent inspection body (TÜV, BV, DNV) | Third-party approval |
EN ISO 15614-1: Qualification Process for Steel
Welding procedure qualification for steel is performed under EN ISO 15614-1. The process involves:
- Prepare pWPS (preliminary WPS): Draft welding parameters.
- Weld the test piece: Using production equipment and personnel under workshop conditions.
- Non-destructive examination (NDE): Visual (VT), penetrant (PT), ultrasonic (UT) or radiographic (RT).
- Destructive tests: Tensile, bend, hardness survey, Charpy impact, macro examination.
- Write and approve WPQR: All results recorded; if acceptable, WPS is formally qualified.
Required Tests
| Test | Acceptance Criterion | Standard |
|---|---|---|
| Tensile | Rm ≥ minimum UTS of base metal | EN ISO 4136 |
| Bend | 4 specimens, 180°, no cracks | EN ISO 5173 |
| Charpy V-Notch | Average energy at WPS temperature ≥ 27 J | EN ISO 9016 |
| Hardness | HV10 — max 380 HV for structural steel (450 HV for S960QL) | EN ISO 9015-1 |
| Macro examination | No cracks, porosity or lack of penetration | EN ISO 17639 |
Range of Approval
A WPS qualified by a WPQR covers a limited range of application. Any weld outside that range needs a new qualification:
- Material group: by ISO/TR 15608 group number (1.1, 1.2, 2, 3, 8.1 etc.). A test in one group also covers certain other groups according to the table in the standard.
- Thickness: for a test piece of 3–12 mm, roughly 0.5t (minimum 3 mm) to 2t; for 12–100 mm, 0.5t to 2t. For single-run or high heat input welds the upper limit is narrower.
- Diameter (pipe): a range starting at half the test diameter is qualified; for small diameters both the lower and upper limits are narrower.
- Position: without impact or hardness requirements, a test in one position covers all others except vertical down (PG); with such requirements the positions with the highest and lowest heat input must be tested.
- Consumables, gas and heat input: where impact requirements apply, heat input may be at most 25% higher than in the test; where hardness requirements apply, at most 25% lower.
Important: EN ISO 15614-1 covers steels and nickel alloys. Welding procedures for aluminium and its alloys are qualified to EN ISO 15614-2. Always check the current tables of the standard for exact ranges.
Routes to Qualify a WPS: EN ISO 15607
Not every welding procedure needs a laboratory test. EN ISO 15607 defines five ways to qualify a WPS:
| Standard | Route | When is it used? |
|---|---|---|
| EN ISO 15614 | Welding procedure test | The most comprehensive route. Usually mandatory for EXC3, EXC4 and pressure equipment. |
| EN ISO 15613 | Pre-production welding test | When a standard test piece cannot represent the real part, a part-like sample is welded. |
| EN ISO 15612 | Standard welding procedure | Use of a published standard procedure; for low-risk work and limited materials. |
| EN ISO 15611 | Previous welding experience | The manufacturer documents successful past production with the same procedure. |
| EN ISO 15610 | Tested welding consumables | Based on consumable approval; the most limited route. |
Under EN 1090-2, routes 15610, 15611 and 15612 can be accepted in EXC2 for certain materials and conditions. In EXC3 and EXC4, procedures must be qualified by an EN ISO 15614-1 test or an EN ISO 15613 pre-production test. So on a project with a high execution class it is not enough for a supplier to say "we have WPQRs"; ask which route they were qualified by.
EN ISO 15614-1:2017 Level 1 and Level 2
The 2017 edition of the standard introduced two test levels:
- Level 1: closer to the ASME IX approach; fewer tests and a wider range of approval.
- Level 2: the traditional European approach; with impact and hardness tests it gives a narrower but more reliable range of approval.
A procedure qualified to level 2 also covers level 1, but not the other way round. Work under EN 1090-2 is based on level 2. When you review a WPQR, the level it was issued to is one of the first things to check.
Validity of a WPQR
A WPQR qualified under EN ISO 15614 is indefinitely valid — no renewal required. However, re-qualification is needed if:
- The welding process changes (e.g. MAG to TIG)
- The material group changes
- Thickness exceeds the qualified range
- Consumables change significantly
ArmaWeld WPS/WPQR Library
ArmaWeld holds 80+ approved WPS and WPQR records covering carbon steel (S235–S355), high-strength (S690QL, S700MC, S960QL), stainless (304L, 316L), aluminium alloys (5083, 6082) and wear steels (HARDOX 400/450/500).
Checklist for Reviewing a Supplier's WPQRs
When your purchasing or quality team reviews a supplier's WPQR list, ask these questions:
- Process: is the process for your part (for example 135 or 121) on the list?
- Material group: is your steel (for example S355 group 1.2, S690QL group 3) within the qualified groups?
- Thickness and diameter: are your thinnest and thickest parts within the qualified range?
- Joint type: a butt weld qualification covers fillet welds, but not the other way round. If you have full-penetration butt welds, a butt weld qualification is required.
- Impact test temperature: if the project requires impact values at -20 °C or -40 °C, the WPQR must have been tested at that temperature.
- Heat treatment: if the project requires PWHT, the WPQR must have been made on a heat-treated test piece.
- Examining body and level: who signed the document, and to which standard and level was it issued?
How Long Does a WPQR Take?
Welding the test piece and non-destructive testing are usually finished within a few days. Destructive tests can take one to three weeks depending on the laboratory's workload. For a material or thickness without a qualification, this time has to be planned at quotation stage. With a supplier whose existing WPQRs already cover your job, the waiting time disappears completely.
At ArmaWeld: at quotation stage we compare your drawing with our existing WPS/WPQR list. If no procedure covers your job, we state this clearly in the quotation and add the test time to the delivery schedule. See our quality and certificates →
Frequently Asked Questions
What is the difference between a WPS and a WPQR?
A WPS is the instruction that tells the welder how to weld. A WPQR is the record of the inspection and test results of a test piece welded to that instruction, proving that the procedure works.
Does a WPQR expire?
A WPQR qualified to EN ISO 15614-1 does not expire. But if an essential variable (process, material group, thickness range, heat treatment and so on) changes, a new qualification is needed.
Who approves a WPQR?
An independent examining body (for example TÜV, Bureau Veritas, DNV) that witnesses the tests and evaluates the results. For pressure equipment this body must be a notified body or a recognised third-party organisation.
Can a WPQR be used by another company?
No. A WPQR is tied to the manufacturer that carried out the test and to its technical control. Another company's WPQR cannot be taken over.
Need WPS/WPQR Support?
Contact our engineering team for welding procedure preparation and qualification services.
Get in Touch →